ASRS

We STREAMLINE your ASRS

Common Tasks:

  • Develop conceptual ASRS design 

  • Simulate workloads and material flows to assess feasibility

  • Prepare detailed RFP for selected ASRS vendors

  • Integrate conveying system, support processes and IT interfaces 

  • Evaluate ASRS vendor proposals and develop recommendation

  • Perform detail design and value engineering with selected vendor

Methods and Tools:

  • Material Flow Analysis

  • Workload Analysis

  • Performance Simulation & Verification

  • Vendor Evaluation Matrix

Reference Industries:

  • Pharmaceuticals

  • Chemicals

  • Automotive

  • Parts and Components

  • Building Materials

  • Consumer Goods

Ø Project Duration:

Ø Project Payback:

8 - 12 weeks​

4 - 6 months

bottom line optimization 10 - 25%

Reference Project: ASRS Design & Value Engineering

Industry:

Company Size:

Project Location:

Global Pharmaceuticals Manufacturer

30,000+

United States

Problem Statement:

As part of a greenfield plant expansion, our customer requested support for the design of an automated storage and retrieval system (ASRS). In a first step, the projected storage demand, the required retrieval performance, material flows and interfaces to IT as well as to the plant conveyor system were to be identified and mapped. Based on this conceptual information, an RFP was to be developed and sent to multiple ASRS vendors. Through a comprehensive vendor evaluation and value engineering process, the best-fit ASRS solution was to be selected for implementation.

STREAMLINERS' Approach and Solution

Meeting:

Overview of the architectural plans and footprints of the site and the outlines of the planned building; high level understanding of the planned ASRS functionality

Deep Dive:

Analysis of projected handling units, workloads and support processes; understand planned operating hours and shift model

Hypothesis:

After analyzing all forecast-, process- and workload related data, the main focus of the ASRS design must lie on the performance parameters, especially the retrieval rate. While additional storage capacity can be outsourced externally, the pallet retrievals to feed production as well as finished goods shipping have to be performed solely within the ASRS on site.

Project:

1 consultant

12 weeks

Deliverables:

Storage and retrieval workloads based on projected data simulated

Conceptual design of ASRS, support processes and conveyors developed 

Detailed RFP for ASRS vendors created and sent out

Vendor evaluation based on their proposals and solutions

Detail design and value engineering with selected ASRS vendor

Bottom Line Impact:

Required footprint reduced by 20%

Developed and selected solution 9% below budget 

ASRS Vendor Selection

Graphics_ASRS.png

Fees vs. Bottom Line Impact

Graphics_ASRS_Impact.png