Common Tasks:

  • Redesign of material flows to reduce waiting, motion and transportation waste

  • Develop new plant layout, fitted to actual (new) process and material flows

  • Implement conveying technology to speed up material flows

  • Align material flows and production/assembly tact to avoid excess work in progress (WIP)

  • Incorporate pull systems (Kanban) to increase flow

Methods and Tools:

  • Material Flow Analysis

  • Process Mapping/VSM

  • Lean Assessment

  • Waste Walk

  • Continuous Process

  • Kanban

Reference Industries:

  • Manufacturing

  • Automotive

  • Engineering

  • Parts and Components

  • Food

  • Building Materials

Ø Project Duration:

Ø Project Payback:

6 - 10 weeks​

3 - 6 months

bottom line optimization 15 - 25%

Reference Project: Material Flow Optimization

Industry:

Company Size:

Project Location:

Global Pharmaceuticals Manufacturer

30,000+

United States

Problem Statement:

Due to increased market demand, our client was forced to rapidly improve the production output at one of their US plants in order to avoid stock-outs and customer complaints. The client's operations executive team had identified the poor material flows at that facility as a main constraint on their path for growth. If the plant would not radically improve their internal material flows, the required production output to meet customer demand would for sure be missed.  

STREAMLINERS' Approach and Solution

Meeting:

Definition of problem statement and scope

Deep Dive:

Understand current material flows, bottlenecks and process constraints in detail to reveal optimization potentials and to draft alternative material flow scenarios

Hypothesis:

Design and implement optimized material flows to drastically reduce required storage capacity, footprint and to significantly improve output performance 

Project:

1 consultant

8 weeks

Deliverables:

Optimized material flows implemented

Required storage capacity reduced by 25%  

Output performance improved by 13% due to redesigned conveyor system

Outbound freight reduced by 23% due to optimized handling units

Bottom Line Impact:

Output performance improvement 13%

Annual freight savings >$0.8 M

Waste Analysis

Graphics_Material Flows_Material Flow Ra

Fees vs. Bottom Line Impact

Graphics_Material Flows_Impact.png